|

Sunshine
Coast Regional District
Chapman Creek Water Treatment
Plant
The
Sunshine Coast Regional District (SCRD) is located 40 minutes by ferry
northwest of Vancouver on the beautiful Sunshine Coast. The SCRD supplies
water to residents with five separate water systems consisting of seven
supply sources. The largest system is the Chapman Creek system which
supplies
water
to 22,000 residents in Sechelt and adjoining rural areas.
In
late 2001,
the SCRD received approval of a $3.8 million Canada/BC Infrastructure Grant
to construct a water
treatment plant for the Chapman
Creek water system. In 2002 the SCRD hired an engineering consultant,
reviewed process designs, approved the detail project design and tendered
the project. The total project cost was $7,000,000. The water treatment
plant construction began in February 2003.
WATER SOURCE
Water
from Chapman Creek is categorized
as a very soft, coloured, low turbidity, low
pH, high organic carbon, low alkalinity and calcium
deficient water. This combination of
characteristics results in a water that is very corrosive
and is subject to formation of disinfection
byproducts including trihalomethanes and haloacetic acids
when using chlorine for disinfection. The water quality is
quite good
for most
of the year, however colour and turbidity levels exceed
drinking water guidelines during
spring runoff and following heavy rains.
|
Nominal
Flow
|
25 ML/day
|
Hydraulic Capacity
|
32 ML/day
|
Average Daily Flow
|
12.5 ML/day
|
Minimum Flow
|
9.0 ML/day
|
Maximum Flow
|
25 ML/day
|
WATER SUPPLY
Water flows
from the intake on Chapman Creek through an existing sedimentation
box, where the water flow is
slowed to allow settling of sand which
can be manually flushed out. Water then travels by gravity pipeline
for approximately one kilometer to a new raw water pumping station.
This
pumping station consists of three low lift pumps which supply all
the flow to the new treatment
plant.
Each pump has a capacity
of 16 ML/day and operates on variable speed drives. Two pumps
only can
operate together. The raw water is pumped to the main treatment
plant building which is adjacent to the existing 13 ML Selma
Zone 2 reservoir.
PLANT PROCESS
The water treatment plant process consists of chemical injection and
rapid mixing, coagulation and flocculation, clarifying by flotation,
filtration and disinfection. Treated water is discharged into the adjoining
reservoir prior to entering the distribution system.
 
Rapid Mixing
Raw water enters the plant by a 600 mm water main and passes through
a flow meter which measures total flow and is used to adjust the chemical
feed amounts. The plant uses aluminum sulphate (alum) as a coagulant,
which is injected at the head of the plant. The liquid alum is rapidly
mixed in the water by a pump and diffuser. Water then flows to a flow
splitter box where soda ash is injected. The soda ash solution increases
the low pH of the raw water.
The flow splitter box divides the water flow into
two pre-treatment process trains. Each train consists of two flocculation
tanks and one
DAF tank. Following this are four filters. During lower flows from
October to April, one process train and two filters are in operation;
with both trains and four filters required for the spring and summer
month’s operations.
Coagulation and
Flocculation
Alum is used as the coagulant, which results in the clumping together
of fine particles which cause colour and turbidity, into larger particles
called floc. Once the alum has been injected into the raw water, the
water enters the flocculation tanks where it is gently mixed. The flocculators
are mechanical paddle mixers with one mixer in each tank. The first
tank mixing is done at about twice the speed as the second tank. Detention
time at maximum flow is 23 minutes.
Flocculation Tanks
|
4 (2 per train)
|
Volume per cell
|
110 m3
|
Water depth
|
4.40 m
|
DAF Clarification
Water leaves the flocculation tanks entering into the bottom of the
dissolved air flotation (DAF) tanks. There is a slanted baffle plate
in the first section of each DAF tank where aerated water is injected
from recycled lines. Millions of microscopic air bubbles (20 - 50 micron
diameter) are released and float to the surface of the DAF floating
the floc particles to the water surface. This floc is skimmed by a
continuously rotating skimmer brush and sent to waste. Clean water
is collected at the bottom of the DAF through launder pipes that lead
to the filter influent channel.
DAF tanks |
2 (1 per train) |
DAF size |
5 m X 9.5 m |
Water depth |
3.9 m |
Surface loading |
12.2 m/hr |
Maximum flow |
13.9 ML/day per chamber |
Filters
Water is diverted to any of the four filters from the filter distribution
channel. Polymer is added as a filter aid and also added to backwashed
waste water. The rapid rate filters are gravity down flow filters with
dual media – 500 mm of anthracite on top of 250 mm of sand. The
filters are backwashed from a submersible pump pumping treated water
and air scoured by one of two blowers.
Filters |
4 |
Filter size |
6.1 m X 3.6 m |
Water depth |
3.0 m |
Filter media |
500 mm anthracite |
|
250 mm sand |
Disinfection
UV light is used as the primary disinfection system just before the
treated water leaves the plant. Chlorine gas is the secondary disinfectant,
added first in the filter distribution chamber before water enters
the filters, then also in the effluent chamber as the treated water
leaves the plant prior to flowing into the 13 ML reservoir. Chlorine
is also added as required as the treated water leaves the reservoir
for the distribution system.

Soda ash is also injected in the effluent chamber once the treatment
process is complete, again to raise the pH of the treated water.
Residuals
The treatment process produces sludge from the removal of colour and
turbidity in the DAF and filter processes. Floc from the DAF process
and backwash waste from the filters is flushed by gravity to the old
open water reservoir 1.5 km from the water treatment plant. The old
reservoir was converted to a sludge settling basin where the water
is decanted and piped to an adjacent gravel and sand operation.
PLANT CONTROLS
Two new standby diesel generators are available for automatic switchover
in case of a power outage. A 450 kW generator powers the main plant
with a 100 kW unit powering the raw water pump station. An existing
35 kW generator powers the chlorine building in case of a power outage.

The new plant has a networked SCADA system allowing for onsite plant
operation with data logging and report generation, and remote monitoring
and alarming through the SCRD monitoring system.

STAFFING
The plant is operated with one operator on day shift,
seven days a week. There are four trained operators who share the work
on a rotational basis throughout the year. The four operators, Dennis
Cassin, Shane Walkey, Scott Fry and Gary Popp were all existing SCRD
waterworks employees prior to training at the new plant.

The Chapman Creek Water Treatment Plant was commissioned
in March 2004, supplying safe and excellent quality water to Sunshine
Coast residents and visitors.
Don Gare
SCRD
|